Specific to HESCO

What differs for HESCO consumers

National ENC portal
Serves HESCO. You can complete this on enc.com.pk without visiting an office.
HESCO helpline
022-111-786-786
Service area
Hyderabad, Nawabshah, Mirpurkhas, Badin, Tando Adam, Shaheed Benazirabad
What that means locally
HESCO's territory centers on urban Hyderabad and Nawabshah/Shaheed Benazirabad, with Mirpurkhas, Badin, and Tando Adam covering Sindh's cotton- and rice-growing interior — new connections in the coastal/canal-belt districts more often carry agricultural tube-well load alongside domestic demand than the more purely residential Hyderabad city grid.

The documents, fees and stage-by-stage flow are set nationally and are the same for every DISCO — they are written up once on the change-application process page rather than repeated here.

Change Application — HESCO

HESCOChange Application — Name, Tariff & Load

Changing the name, tariff, or sanctioned load on an existing HESCO meter goes through the same change-application workflow used nationwide, minus the pole-and-cable survey in most name/tariff cases. HESCO's territory centers on urban Hyderabad and Nawabshah/Shaheed Benazirabad, with Mirpurkhas, Badin, and Tando Adam covering Sindh's cotton- and rice-growing interior — new connections in the coastal/canal-belt districts more often carry agricultural tube-well load alongside domestic demand than the more purely residential Hyderabad city grid.

Change of Name
Change of Tariff
Load Enhancement
022-111-786-786

Which Change Application Do You Actually Need?

HESCO runs three separate change-application tracks, and each carries its own documents, fee structure, and timeline. Applying under the wrong one wastes weeks rather than saving them — work out which one matches your situation before you touch the form.

Change of Name — Ownership Transfer

15–30 working days

This moves the meter's registered name from a previous owner to you. It's needed after a property purchase, an inheritance, a gift transfer, or any other legal change of ownership. HESCO's billing records have to match the current ownership paperwork before a change goes through, and any dues still outstanding under the old owner's name must be cleared first — that part isn't negotiable.

You need this when:

  • You bought a property and the meter still carries the seller's name
  • The registered owner has passed away and the property was inherited
  • Ownership changed through a gift deed or a court order

Change of Tariff — Category Switch

10–20 working days

A tariff change updates the billing category — most often domestic to commercial when a business starts operating out of the premises, or the reverse when it closes. The category sets your per-unit rate directly, so billing under the wrong one is treated by HESCO as an irregularity that can trigger retrospective adjustments, fines, or disconnection. If how you're using the connection has genuinely changed, get the paperwork in early rather than after an inspection flags it.

You need this when:

  • A shop, clinic, or salon is now operating from what was a residential meter
  • Your property switched from commercial to purely residential use
  • A registered business at the address has shut down

Change of Load — Enhancement or Reduction

30–60 working days

Every HESCO meter carries an approved kW ceiling — 5 kW, 10 kW, 25 kW, whatever was sanctioned at connection. Adding equipment that pushes past it — industrial air conditioning, machinery, heavy refrigeration, welding gear — means applying for enhancement before you switch it on. Running over the sanctioned limit causes repeated tripping, damages equipment over time, and if an inspection catches it, brings a fine and a forced reduction. Load reduction runs the same process in reverse and lowers your security deposit.

You need this when:

  • You're bringing in industrial or heavy commercial equipment
  • The connection trips repeatedly even without an obvious overload
  • You want the sanctioned load reduced to cut the security deposit

Found the right application type? Apply online now.

Submit your change application directly on the official HESCO portal. Keep your meter or account number and CNIC handy.

Apply at Official Portal →

Redirects to the official government portal.

How to Submit Your HESCO Change Application — Step by Step

All three change types run through the same process, though the documents and fees at each step differ. Work through these in order — skipping a step, especially the document upload or the payment, is what stalls an application.

1
You

Step 1 — Confirm Which Application You Need

Match your situation against the three types above — name, tariff, or load. Genuinely unsure, especially where a sale and outstanding dues overlap? Call 022-111-786-786 before submitting anything. Picking the wrong category means cancelling and starting over, which costs days you don't get back.

Note: Have the meter account number and a recent bill on hand before you call.
2
You

Step 2 — Clear Whatever Is Outstanding

HESCO checks for unpaid bills on the meter before it reviews anything else. Unpaid dues are the single biggest reason change applications — name changes especially — stall or get rejected outright. Check the current balance on the latest bill or by calling the helpline, and settle it before or alongside submitting.

Note: Download the current bill through Electricity Bill to confirm the balance first.
3
You

Step 3 — Assemble the Documents

Pull together whatever your application type requires (see the table further down). CNIC attestation trips people up most — self-attested or unstamped copies get bounced. Name changes need ownership transfer papers that clearly establish legal title; load changes need a report from a WAPDA-licensed wiring contractor.

Note: Scan at 300 DPI, JPEG or PDF, each file under 2MB.
4
You

Step 4 — File the Application Online

Log in to the HESCO portal (link above), enter your existing meter or account reference number, and select the application type. Fill in every required field, attach the documents, and submit. Your Tracking ID arrives by SMS on your registered mobile — save it somewhere you won't lose it.

Note: Use the mobile number your meter account is actually registered under.
5
HESCO

Step 5 — Verification, and a Survey if Needed

Name and tariff changes go through document verification, usually 5–15 working days. Load enhancement adds a field survey — an engineer checks whether the existing cabling, service line, and area transformer can take the higher load. The visit isn't always announced in advance, so keep someone at the property and the relevant area clear.

Note: Check the application status every few days through this stage.
6
You

Step 6 — Pay the Demand Notice

Once verification is done, HESCO issues a Demand Notice covering whatever's chargeable — the processing fee, infrastructure upgrades for load work, or a security deposit adjustment. Print it, pay at a listed bank, and upload the receipt the same day. Name and load changes usually carry a fee; a straightforward tariff switch sometimes doesn't.

Note: Demand Notices expire — don't let one sit unpaid past its date.
7
HESCO

Step 7 — The Change Takes Effect

Once payment clears, HESCO updates the billing system. Load enhancement may involve a crew visit to upgrade cabling, the CT meter, or fuse capacity. Your next bill should reflect the new name, tariff, or load — if it doesn't, call the helpline the same day that bill arrives. Corrections get harder to push through the longer they sit.

Note: Check your first post-change bill and keep the Tracking ID handy in case you need it.

Outstanding Dues — The Change Application Blocker

HESCO won't touch a name-change application while the meter carries any unpaid balance — that includes the current month's bill, reconnection charges, and penalty amounts. Check the balance on the latest bill, pay off whatever's outstanding, and keep the receipts. Even after paying online, allow 2–3 banking days for it to register in the HESCO system before you submit the change application.

Required Documents by Change Type

Cross-check this table against your paperwork before you submit. For every type, bring the originals along with attested copies in case an office visit is required.

DocumentName ChangeTariff ChangeLoad Change
Applicant's attested CNIC copy
Latest electricity bill copy
Witness attested CNIC copy
Property transfer deed / sale deed
Court succession certificate (inheritance)If applicable
Current owner's CNIC or NOC
Business registration (SECP/FBR)
Affidavit of business closure (residential reversal)If applicable
Wiring contractor test report
Load assessment certificate (licensed contractor)

Realistic Timelines — What to Expect

How long a change application takes depends on the type, how complete your documents are, and how fast you respond at each checkpoint. Here's an honest breakdown:

Change of Name

15–30 working days

Slow factors: Missing property transfer docs, outstanding dues

Fast factors: Clean documents, zero outstanding bills

Change of Tariff

10–20 working days

Slow factors: Conflicting evidence of usage type

Fast factors: Clear documentary proof of business/domestic status

Change of Load

30–60 working days

Slow factors: Survey delays, low transformer capacity area

Fast factors: Prompt DN payment, accessible property

About Hyderabad Electric Supply Company (HESCO)

Overview

Hyderabad Electric Supply Company (HESCO) is a NEPRA-regulated electricity distribution company covering Hyderabad, Nawabshah, Mirpurkhas, Badin, Tando Adam, Shaheed Benazirabad and surrounding districts. It is the sole licensed distributor for all residential, commercial, agricultural, and industrial consumers in its service territory.

Change Applications

HESCO processes change applications for every consumer in its territory, all submitted online through the official portal. A physical office visit is only needed if HESCO specifically requests further documentation after reviewing your case.

Customer Helpline

Queries on application status, outstanding dues, or to escalate a stalled change application:

022-111-786-786

Frequently Asked Questions

Common questions from HESCO consumers about change applications, answered plainly.

How do I change the name on a HESCO electricity meter?+

Submit an online change-of-name application through the official portal, entering the current account details alongside the new owner's information. Attach the new owner's CNIC, the property transfer documents, and either the previous account holder's CNIC or a No Objection Certificate. HESCO reviews the documents, may schedule a site visit, and then issues a Demand Notice for the applicable fee. The name updates in the billing system once that fee is paid.

What documents does HESCO ask for on a change-of-name application?+

Expect to provide: (1) an attested CNIC copy for the new owner, (2) proof of the ownership transfer — a sale deed, gift deed, or succession certificate for inherited property, (3) either the previous holder's attested CNIC or an NOC releasing the account, (4) a copy of the meter's most recent HESCO bill, and (5) an attested CNIC copy from a witness.

What counts as load enhancement with HESCO, and how do I request it?+

Load enhancement raises the sanctioned kW ceiling on a connection you already have — going from 5 kW to 10 kW, say, after adding a large air conditioner or a piece of business equipment. Apply by selecting "Change of Load" on the application form. HESCO sends someone to check whether the local transformer and cabling can carry the extra load, then issues a Demand Notice for whatever upgrades are needed before the higher limit takes effect.

How long does a HESCO change application take?+

It depends on the type. Name changes run 15–30 working days — document checks, a possible site visit, the Demand Notice, payment, then the system update. Load changes take longer, 30–60 days, because a technical survey and sometimes infrastructure work are involved. Tariff changes move fastest, 10–20 days, since they're mostly a paperwork check. Whatever the type, check status regularly with your Tracking ID rather than assuming no news is good news.

Does HESCO charge a fee to change the name on a meter?+

Yes — an administrative and processing fee applies, and the amount depends on the transfer type. A same-family transfer via succession certificate is usually cheaper than a commercial ownership change. Any arrears on the meter have to be cleared before the name change goes through, regardless of fee type. The exact figure appears on the Demand Notice once your documents have been checked.

Ready to submit your HESCO change application?

Apply at Official Portal →

More HESCO Services

Track HESCO ApplicationCheck live statusHESCO New ConnectionApply for a new meterPrint Demand NoticeDownload your DNPay Demand NoticeOnline payment (LESCO)Upload ReceiptAfter bank paymentAll ENC ServicesFull directory

اردو میں پڑھیں

This guide is also available in Urdu for HESCO customers.

اردو →